Engineering design: extending foundation pile supportBlind
-
Open
-
Choosing Finalist
-
Ended
The combined assembly is a clamp on system, that clamps onto 36" diameter pipe, then when hydraulic pistons are activated the arms extend and lock out to approximately 45deg.
I have attached schematics showing in 2d what I am after. Potential for significant future work for winning designer.
If you can show neat hydraulic lines from pistons leading to a single point at top of assembly, that would be a bonus.
The arms when collapsed should be as flush with pipe body as possible.
Moreover this is a qualifier for future work, as we have 4 other project designs needing drawings, and work doing.
- SolidWorks
also accept design in 3d autocad, as want to open to more designers.
Entries
- SolidWorks 2017 — Pipe Support GA
- SolidWorks 2017 — 2A-Body-Bore4.00 x
- SolidWorks 2017 — 2A-Rod-Bore4.00-Rod1-STD x
- SolidWorks 2017 — 4.00T2ALY14M13.800 1
- SolidWorks 2017 — 4.00T2ALY14M13.800 2
- SolidWorks 2017 — 4.00T2ALY14M13.800
- SolidWorks 2017 — Arm
- SolidWorks 2017 — Brace
- SolidWorks 2017 — Bush
- SolidWorks 2017 — Clevis
- SolidWorks 2017 — Cylinder Bracket
- SolidWorks 2017 — Cylinder Bracket2
- SolidWorks 2017 — cylinder
- SolidWorks 2017 — GA
- SolidWorks 2017 — Pin
- SolidWorks 2017 — Pin2
- SolidWorks 2017 — Quarter Ring Assembly
- SolidWorks 2017 — Ring Quarter
- Microsoft Excel 2016 — BOM parts
- Video WMV — Exeploded View
- Video WMV — Pile Foundation Support WMV V9
- Video WMV — Pile Foundation Support-2 WMV V9
- Video WMV — Pile Foundation Support-3 WMV V9
- jpg — Pile Foundation Support V2-1
- jpg — Pile Foundation Support V2-2
- jpg — Pile Foundation Support V2-3
- jpg — Pile Foundation Support V2-4
- jpg — Pile Foundation Support V2-5
- jpg — ARM Assy
- jpg — ARM Assy-2
- jpg — ARM sheet metal base plate
- jpg — ARM sheet metal plate
- SolidWorks 2017 — GA Draft2
- SolidWorks 2017 — Arm
- SolidWorks 2017 — Cylinder Clevis
- SolidWorks 2017 — Spacer Washer
- SolidWorks 2017 — Pin Type 3
- SolidWorks 2017 — 2A-Body-Bore4.00 x
- SolidWorks 2017 — 2A-Rod-Bore4.00-Rod1-STD x
- SolidWorks 2017 — 4.00T2ALY14M13.800
- SolidWorks 2017 — Brace
- SolidWorks 2017 — Bush
- SolidWorks 2017 — Cylinder Bracket
- SolidWorks 2017 — GA
- SolidWorks 2017 — Leg
- SolidWorks 2017 — Pin
- SolidWorks 2017 — Pin3
- SolidWorks 2017 — Pipe
- SolidWorks 2017 — Quarter Ring Assembly
- SolidWorks 2017 — Ring Quarter
- SolidWorks 2019 — Assem foundation pile support
- ImageJ — Capture1
- ImageJ — Capture2
- ImageJ — Capture3
- ImageJ — Capture4
- ImageJ — Capture5
- ImageJ — Capture1.1
- ImageJ — Capture1.2
- ImageJ — Capture1.3
- ImageJ — Capture1.4
- ImageJ — Capture1.5
- video — Assem Hydrolic movement
- video — Assem rotat and exploaded 1 Fadi
- Video - WMV — Pile Foundation Support WMV V9
- Video - WMV — Pile Foundation Support-2 WMV V9
- Video - WMV — Pile Foundation Support-3 WMV V9
- jpg — Pile Foundation Support
- jpg — Pile Foundation - Support-
- jpg — Pile Foundation Support-1
- jpg — Pile Foundation Support-2
- jpg — Pile Foundation Support-3
- jpg — Pile Foundation Support-4
Discussion
Showing last 20 comments - View AllThank you
Designer
Buyer
Some really excellent efforts, due to the volume of design entries, and the similarity of many, it will take me a few days to work through all of them based on the original design parameters:
- Similarity to original design brief
- Functionaility in planned environment, robustness, Simplicity of design and ease of construction
- Quality of actual design once uploaded to Solidworks.
The top 5 designers will be invited to future blind design competitions.
Regards, Mark
-CS
Buyer
In response to your questions:
1. The device will be fitted prior to driving the pile, so it will expand with hydraulic and driving motion, to the final 45deg expansion shape.
2. It will be retrieved, so the hydraulic pistons will be used to push the pile out at end of life, for re-use. That is the plan anyway :-)
Please feel free to ask any other questions you may have.
I have started the detailed review process and am currently downloading all designs into Solidworks for analysis.
Regards,
Mark
Regarding this I have two queries viz
1) will the device be installed on the pipe prior to driving the pile or after it has been driven a bit.
2) is the device meant to be used multiple times or is it sacrificial in the sense that concrete will be poured over it as well thus making it a part of the foundation permanently.
I ask these as your request is rather novel.
Thanks
Buyer
1. No existing pictures it is a new system and new use. It needs to be run with the legs collapsed against the pile / pipe body. Then while running into place in very soft formation the hydraulic rams will extend the legs out to approximately 45 deg. You have freedom to come up with different hinge and leg extension mechanism, but overall the system must be able to fold flat against body, with total OD less than 60".
2. Loadings for the pile are tricky, installation loadings will have the hydraulic ram apply up to maximum of 10Mt of force on each leg. Service loadings on the system maybe up to 150 - 200 MT Axially through the pile (most of this will be taken through the pile) and 40 - 80 Mt applied laterally to the top of the pile.
3. The legs need to be able to fully collapse for easy of transport and picking up, the total assembly OD should be less than 60".
4. The legs should be able to withstand approx 100 kN m of bending force (the detailed engineering and design of these is not part of this competition)
5. If any one is able to undetake FEA, this would be a big benefit.
Designer
Designer
I have a doubt about the point E in the part 3 is it able to move up and down if not will not be like top view assemble will be like the design I have sent. please contact me to discuss more. thanks
Designer
Designer
Designer
Designer
Designer
Designer
Buyer
Designer
What that is mean ( Explosion diagram)?Is there any potential explosion risk?Is there any ATEX classification?Is it explosion hatch or not? What is the meaning of the pipe clamp?
Buyer
I will pre-pay and add a 2nd prize as well.
"3 parts" was just referencing trying to reduce different parts, to try and stadardise for simplicity. If there are more parts, but the design is better / simpler then that will be a good solution too.
Mitch, in response to your questions:
- This structure is to stabilise the pile as it is taking lateral loadings in shallow and weak soil conditions.
- the pile will be installed by crane
- The pipe within this device is the structural pile, it will be jetted into place or possibly installed in a predrilled hole and cemented.
Regards, Mark